Webster Library Transformation

About the project

In January 2015, Concordia’s R. Howard Webster Library begins a profound transformation that will reshape its physical spaces and learning environment in line with those of next- generation libraries. A next-generation library provides:

  • Space for active and collaborative learning; an on-campus social learning environment.
  • Space where students take command of their own learning.
  • Opportunities for intensive study.

This project – an important academic priority – is part of Concordia’s overall plan to reinforce the Libraries’ ability to support learning and research activities; provide a foundation for intellectual life within Concordia, and foster a culture of research and innovation, and collaborative learning.

Addressing the longstanding need for quality study spaces is an important element of this project. This was concern raised by students in university-wide surveys on library spaces, services and collections conducted in 2010 and 2013.

Project need

When the Webster Library opened in 1992, Concordia had a population of 16,000 students. Today, the student population has nearly tripled, which means a dramatic increase in people who visit the Library – an average of 2.2 million visitors per year.

According to the Ministère de l'Enseignement supérieur, de la Recherche et de la Science, the current total library space at the Webster Library and Vanier Library is 38 per cent below established norms, which is a shortage of 9,500 m2.

At present, only .57 m2 of space is allocated for each full-time equivalent (FTE) student. This ranks as the lowest space per FTE among comparable Quebec and Canadian university libraries.

Project approval

In June 2013, after reviewing preliminary plans for the renovation and expansion of the R. Howard Webster Library, Concordia’s Board of Governors gave its approval for the preparation of detailed design plans.

On October 22, the project reached another milestone with the approval by the Board, during its closed session, to proceed with the next phase. This includes the awarding of the construction, professional and supply contracts following the tender process.

Project funding

The majority of project funding is coming from the Government of Quebec under budget envelopes earmarked for university infrastructure projects and equipment. There is also a substantial financial contribution from students.

11 types of study spaces
  1. Tables for silent study
  2. Graduate students study spaces
  3. Carrels for silent study
  4. Classrooms and technology sandbox
  5. Tables with desktop computers
  6. Consultation rooms
  7. Multi-functional/social areas
  8. Seminar and thesis defense room
  9. Group study rooms
  10. Multi-functional / zero-noise room
  11. Presentation practice rooms
Construction phases
PhaseDates
Phase 1: LB3 East January 2015 - July 2015
Phase 2: LB5 July 2015 - March 2016
Phase 3: LB2 May 2016 - January 2017
Phase 4: LB3 West and LB4 East March 2017 - October 2017
Consultations

A series of consultations will be held during the project’s lifecycle to obtain feedback on furniture and technology.

Library access

The Webster Library will remain open throughout the renovation project. We will contain most of the renovations inside noise-insulated walls to reduce potential disruptions.

Students will also have access to the Georges P. Vanier Library on the Loyola Campus and the Grey Nuns Reading Room on the Sir George Williams Campus.

Keep informed

We will provide regular updates and news via our social media channels, through the NOW newsletters and on our Webster Library Transformation Blog: https://library.concordia.ca/webster-transformation/